Severely outdated Community Infrastructure Levy (CIL) rates are actively holding back housing and commercial development across England. While councils cannot control the wider economic headwinds facing the property sector, they do control their own local regulatory burden—yet too many are failing to use that lever to stimulate growth.
The capital offers a telling example. In an irony not lost on the sector, the time-limited relief from borough CIL announced by the Government and the Mayor of London as part of their October 2025 ‘emergency measures’ package has yet to materialise, more than a year on. Worse, the prospect of that relief is likely to give boroughs another reason to delay reviewing their own CIL rates. Across the country, developers are left to navigate charging schedules that are fundamentally disconnected from today’s economic reality.
The Original Promise of CIL
CIL came into force in 2010 to ensure that infrastructure kept pace with housing growth. Newark and Sherwood District Council was an early pioneer, adopting its first charging schedule in September 2011, and the London Borough of Redbridge followed in November 2011, with its charges taking effect in January 2012. Before CIL, authorities relied on section 106 (S106) agreements, as Liverpool and every Greater Manchester authority except Trafford still do today. However, because S106 obligations are restricted to mitigating the site-specific impacts of development, they are notoriously slow to negotiate and ill-suited to pooling funds for cumulative, area-wide infrastructure. CIL was therefore intended to be a simple, transparent alternative that spread the burden fairly. Unfortunately, the way CIL is now applied in many areas has strayed far from these founding principles.
How Mechanical Indexation Distorts Viability
When setting CIL rates, Regulation 14 of the CIL Regulations requires charging authorities to strike an appropriate balance between the desirability of funding infrastructure and the potential effects of the levy on the economic viability of development across their area. That balance is not meant to be struck once and then left alone. The Planning Practice Guidance (PPG) states that charging authorities “must keep their charging schedules under review” and should ensure that levy charges remain appropriate over time (Paragraph 045, Reference ID: 25-045-20190901). In particular, reviews should take account of changes in market conditions, rates should remain relevant to the funding gap for the infrastructure needed to support development, and authorities should consider the impact of revised rates on future planned development. Crucially, however, the law does not prescribe when reviews should take place, leaving the timing entirely to each authority’s discretion.
Some early adopters have revisited their rates: Newark and Sherwood, for example, adopted a revised charging schedule following a full review in December 2017. Yet many authorities have not reviewed their rates since they were first introduced more than a decade ago. The London Borough of Redbridge—the first London borough to introduce CIL—has not reviewed its rates since they took effect in January 2012. Instead, these councils have relied entirely on mandatory annual indexation.
Since the CIL (Amendment) (England) Regulations 2019, rates have been updated automatically each year using the RICS CIL Index. Although this is intended to keep infrastructure funding in step with inflation, it creates a fundamental economic mismatch. CIL is, in principle, a charge on the uplift in land value that development creates, yet indexation ties it to construction cost inflation. When build costs surge, the CIL bill rises at precisely the moment development margins are being squeezed, causing serious distortions to viability.
Mechanical indexation has driven substantial increases over the rates originally adopted. Because the RICS CIL Index applies nationally, the size of that increase depends on when a schedule was adopted, not where. London boroughs illustrate the pattern:
- 2012–2013 schedules have risen by about 75–80% (including Redbridge, Wandsworth, Brent, Harrow and Croydon).
- 2014 schedules have risen by about 67%.
- 2015 schedules have risen by about 54%.
- 2020–2022 schedules have still seen increases of around 20% (including Camden, Tower Hamlets, Barnet, Lambeth and Bromley).
- 2024 schedules, such as Greenwich’s, have already risen by about 5%.
Because indexation tracks build costs rather than real-time development values and margins, these heavily inflated rates have become detached from commercial viability. The problem is compounded by the fact that schedules adopted in 2012–2014 were tested against a policy and regulatory landscape that no longer exists. Their viability evidence could not account for substantial new cost burdens, including higher affordable housing requirements, the implications of the Building Safety Act 2022, the Building Safety Levy, BNG and updated environmental standards. As a result, developments today are being charged at 2026 indexed rates that remain anchored to outdated viability assumptions.
Collection Without Delivery: The Infrastructure Bottleneck
This financial strain is made all the more frustrating by the way collected funds are deployed. The Home Builders Federation’s (HBF) February 2026 report, Unspent Developer Contributions, estimates that councils across England and Wales hold approximately £2.2 billion in unspent CIL and £6.6 billion in unspent S106 contributions. Much of this money is not new: the HBF found that a third of unspent S106 contributions have been held for more than five years, and estimates that almost £3 billion of developer contributions overall has gone unspent for more than half a decade.
The largest sums are concentrated in London. According to the same report, Brent (£178m), Wandsworth (£117m) and Tower Hamlets (£107m) top the table of unspent CIL balances among councils that supplied data. The problem is not confined to the capital, however: Wiltshire (£49m) and Mid Suffolk (£47m) complete the top five. Councils rightly point out that much of this money is allocated to complex, multi-year projects, but the dynamic remains damaging: developers facing severe viability pressures, driven in part by historically inflated CIL rates, are funding infrastructure that is often substantially delayed.
Urgent Reforms to Unlock Development
The regulatory position is stark. Continuing to apply an outdated CIL rate that renders schemes unviable may not, in itself, be unlawful—the Regulation 14 balance is tested when a charging schedule is examined and adopted—but it falls well short of what the Government’s PPG expects. Doing nothing can no longer be the default approach.
With CIL now acting, in many cases, as a barrier to development, the system requires immediate and radical intervention through the following reforms:
- Deliver Immediate Relief: The Government must bring the proposed London CIL relief into force without further delay and keep it available for as long as is needed to secure strong, sustained housing delivery and economic growth, rather than limiting it to schemes commencing before 31 March 2030. It should also consider whether comparable time-limited relief is warranted in other parts of the country where CIL is holding back otherwise viable development.
- Make Regular Review a Legal Requirement: The PPG already states that charging authorities must keep their schedules under review, but the law does not prescribe when reviews should take place and there is no consequence for failing to carry them out. The CIL Regulations should place a statutory duty on charging authorities to review their rates at fixed intervals and to demonstrate, through up-to-date viability evidence, that those rates remain viable. Authorities whose CIL rates have not been comprehensively reviewed in the last three years should be legally prohibited from applying them until a new viability review is complete. In the interim, they should revert to S106 agreements to secure infrastructure contributions on a viable, site-by-site basis. S106 has well-known shortcomings, as set out above, but it at least rests on negotiation in which the viability of each scheme must be taken into account—something the current CIL regime, with its fixed and mechanically indexed rates, fails to do.
- Overhaul the Indexation Mechanism: The RICS CIL Index requires fundamental review. The mechanical link between construction cost inflation and CIL rates must be broken to prevent future viability distortions, for example by indexing rates to a measure that reflects development or land values.
- Introduce Mandatory Spending Deadlines: Accountability must extend to how collected funds are used. Councils should be required to spend CIL and S106 receipts within a fixed period (say, three years of receipt), and any funds not deployed within that period should be returned to the developer. Return clauses already feature in many S106 agreements, typically with a five-year deadline, but the HBF found that they are rarely used in practice: over half of councils reported returning no S106 funds at all in the past ten years.
Reducing or suspending a headline CIL rate may seem counterintuitive for cash-strapped authorities, but an adjusted rate that actually allows development to proceed generates vital infrastructure funding. A rigid, outdated rate that prevents development altogether yields nothing—and, as we all know, 100% of nothing is exactly nothing.